Fakta om udbudet
Bestilling af materiale
http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=180521&B=DTU
Udbyder
Danmarks Tekniske Universitet / Technical University of Denmark
Vindere
(29.07.2017)
VON ARDENNE GmbH
Dresden
Industrialisation of coated X-ray mirror plate production
Danmarks Tekniske Universitet / Technical University of Denmark
Contract notice
Supplies
Section I: Contracting authority
30060946
Anker Engelunds Vej 1
Kongens Lyngby
2800
Denmark
Contact person: Johanne Pedersen
Telephone: +45 45250207
E-mail: jolip@adm.dtu.dk
NUTS code: DK012
Internet address(es):
Main address: www.dtu.dk
Address of the buyer profile: https://eu.eu-supply.com/ctm/Company/CompanyInformation/Index/165863
Section II: Object
Industrialisation of coated X-ray mirror plate production.
The overall objective of this activity is to design, implement and demonstrate an SPO mirror plate production facility. The facility shall be fully compliant with the Athena requirements. The facility design developed under this activity shall be compliant with the required plate production rate and volume.
The overall objective of this activity is to design, implement and demonstrate an SPO mirror plate production facility. The facility shall be fully compliant with the Athena requirements. The facility design developed under this activity shall be compliant with the required plate production rate and volume.
The tenderer should be aware that the acquisition of the products is part of a project financed by the European Space Agency, ‘ESA’, which is executed by DTU and cosine Research BV.
The service part of the contract consists of 5 times 1 year options.
Section III: Legal, economic, financial and technical information
— A description of each delivery.
— Information on when it was carried out.
— The size and value of the deliveries.
— The recipients of the deliveries.
This must be described in the ESPD part IV.C.
The tenderer must document one similar delivery (understood as sputter system).
Section IV: Procedure
Section VI: Complementary information
The tenderer must use the European Single Procurement Document as provisional evidence in replacement of certificates issued by public authorities or third parties confirming that the tenderer fulfils the minimum requirements.
DTU shall exclude a tenderer from participation in the tender procedure, if the candidate is subject to one of the mandatory exclusion grounds. The candidate shall submit information in this respect in the European Single Procurement Document. Special attention is drawn to the fact that certain voluntary exclusion grounds have been made mandatory. Please refer to The Danish Competition and Consumer Authority's guidance note for correct completion of the European Single Procurement Document.
Please note that in relation to section III.1.3, a tenderer may rely on the capacities of other entities (eg. a parent or sister company or a supplier), regardless of the legal nature of the links between them. In this case, the tenderer shall ensure that DTU receives his own European Single Procurement Document together with a separate European Single Procurement Document with the relevant information for each of the entities that the candidate relies on. Additionally, where the tenderer wants to rely on the capacities of other entities, the tenderer shall prove to DTU that it will have at its disposal the resources necessary, for example, by producing a commitment or other documentation from those entities confirming their legal obligation to provide the necessary resources for the duration of the contract, eg. by completing the form for submission of commitment which is available as part of the tender material. This form for commitment must be sent to DTU as part of the documentation for the information stated in the ESPD.
Finally when groups of entities, including temporary joint ventures, participate in the tender procedure together, each of the participating entities must complete a separate European Single Procurement Document with the information required in section II-IV. A declaration for consortium must be sent to DTU as part of the documentation for the information stated in the ESPD.
Tenderers must submit their offer via EU-Supply.
The application for offer cannot be submitted by e-mail. Reference is made to the detailed description in the tender documents.
Nævnenes Hus, Toldboden 2
Viborg
8800
Denmark
E-mail: klfu@erst.dk
Internet address:http://www.klfu.dk
Pursuant to Danish Act on The Complaints Board for Public Procurement (act no. 492 of 12.5.2010 with subsequent amendments — available at www.retsinformation.dk ), the following time limits for filing a complaint apply:
Complaints must be filed with The Complaints Board for Public Procurement within:
1) 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date).
2) 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision.
3) 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, cf. § 2(2) or § 171(4) of the Act on Public Procurement, provided that the notification included a short account of the relevant reasons for the decision.
4) 20 calendar days starting the day after the contracting authority has published a notice concerning his decision to uphold the contract, cf. § 185(2) of the Act on Public Procurement. The complainant must inform the contracting authority of the complaint in writing at the latest simultaneously with the lodge of the complaint to The Complaints Board for Public Procurement stating whether the complaint has been lodged in the stand-still period, cf. § 6(4) of the Act on The Complaints Board for Public Procurement. If the complaint has not been lodged in the stand-still period, the complainant must also state whether it is requested that the appeal is granted delaying effect, cf. § 12(1) of the said Act. The e-mail of The Complaints Board for Public Procurement is stated in section VI.4.1. The Complaints Board for Public Procurement's own guidance note concerning complaints is available at the internet address stated in section VI.4.1.
Carl Jacobsens Vej 35
Valby
2500
Denmark
E-mail: kfst@kfst.dk
Internet address:http://www.kfst.dk/