Fakta om udbudet
Udbyder
Energinet
132 kV GIS switchgear for substation AVV
Energinet
Contract award notice – utilities
Results of the procurement procedure
Supplies
Directive 2014/25/EU
Section I: Contracting entity
28980671
Tonne Kjærsvej 65
Fredericia
7000
Denmark
Contact person: Ann Sophie Steffensen
Telephone: +45 76224103
E-mail: asa@energinet.dk
NUTS code: DK
Internet address(es):
Main address: https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
Address of the buyer profile: https://eu.eu-supply.com/ctm/Company/CompanyInformation/Index/228008
Section II: Object
132 kV GIS switchgear for substation AVV.
Design, fabrication, inspection, testing, delivery and installation of a 3 phase, 132 kV, 50 Hz, gas insulated switchgear (GIS).
Design, fabrication, inspection, testing, delivery and installation of a 3 phase, 132 kV, 50 Hz, gas insulated switchgear (GIS).
Section IV: Procedure
Section V: Award of contract
132 kV GIS switchgear for substation AVV
27550835
Strevelinsvej 8, Erritsø
Fredericia
7000
Denmark
Telephone: +45 76245330
E-mail: sanne.christensen@ge.com
Fax: +45 76245430
NUTS code: DK
Section VI: Complementary information
Nævnenes Hus, Toldboden 2
Viborg
8800
Denmark
Telephone: +45 72405708
E-mail: klfu@naevneneshus.dk
Internet address:https://erhvervsstyrelsen.dk/klagenaevnet-for-udbud
Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision.
Other complaints must be filed with The Complaints Board for Public Procurement within:
1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date);
2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision;
3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Carl Jacobsen Vej 35
Valby
2500
Denmark
Telephone: +45 41715000
E-mail: kfst@kfst.dk
Internet address:http://www.kfst.dk