Fakta om udbudet
Bestilling af materiale
http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=202004&B=KA
Udbyder
The Danish Defence Acquisition and Logistics Organization (DALO)
Vindere
Lot 1: IBS and IBL
(15.06.2018)
Pro-Safe A/S
Møllevangen 60
4220 Korsør
Opdateringer
II.2) etc.
instead of:
Read:
Additional information
It is DALO’s assessment that some of the minimum requirements for IBOS and IBOL, cf. Lot 2 – Appendix A.1 and A.2, needs to be amended /modified. Therefore, DALO has decided that Lot 2 (IBOS and IBOL) should be omitted (removed) from this tender procedure, i.e. the tender procedure regarding Lot 2 is being cancelled. Please note that DALO expects to publish a separate contract notice regarding a new tender procedure for Lot 2 as soon as possible.
It is emphasized that it is still possible to submit offers for Lot 1 (IBS and IBL) and Lot 3 (RHIBS and RHIBL). Offers must be submitted before the deadline on 19.3.2018, 13:00 hrs., cf. section IV.2.2) of the Contract Notice.
Inflatable Boats and Rigid Hull Inflatable Boats for the Royal Danish Navy
The Danish Defence Acquisition and Logistics Organization (DALO)
Contract notice
Supplies
Section I: Contracting authority
16287180
Lautrupbjerg 1
Ballerup
2750
Denmark
Contact person: Frederik Jastrup Brodersen
Telephone: +45 21550459
E-mail: frjb@kammeradvokaten.dk
NUTS code: DK
Internet address(es):
Main address: www.fmi.dk
Section II: Object
Inflatable Boats and Rigid Hull Inflatable Boats for the Royal Danish Navy
The tender procedure concerns the award of three parallel framework agreements, divided in Lot 1-3, regarding the acquisition of inflatable boats and rigid hull inflatable boats for the Royal Danish Navy.
The contracts (lots) are as follows:
— Lot 1: Inflatable boats small (hereafter “IBS”) and Inflatable boats large (hereafter “IBL”),
— Lot 2: Inflatable boats small (to outboard engine) (hereafter “IBOS”) and Inflatable boats large (to outboard engine) (hereafter “IBOL”),
— Lot 3: Rigid hull inflatable boats small (with outboard engine) (hereafter “RHIBS”) and Rigid hull inflatable boats large (with outboard engines) (hereafter “RHIBL”).
Please note: The tenderer decides for himself whether the tenderer submits offers on 1, 2 or all 3 Contracts (lots), cf. section II.1.6).
Lot 1: IBS and IBL
Lot 1 concerns the acquisition of the 2 boat types, Inflatable Boats Small (“IBS”) and Inflatable Boats Large (“IBL”), for the Royal Danish Navy, cf. Appendix A.1 and Appendix A.2 to the Contract for Lot 1.
The Agreement is entered into by DALO. However, all divisions of the Danish Ministry of Defence, including all units of the Danish Defence subject to the command of the Chief of Defence is entitled to use the Agreement.
Lot 2: IBOS and IBOL
Lot 2 concerns the acquisition of the two boat types, Inflatable Boats Small (to out-board engine) (“IBOS”) and Inflatable Boats Large (to out-board engine) (“IBOL”), for the Royal Danish Navy, cf. Appendix A.1 and Appendix A.2 to the Contract for Lot 2.
The Agreement is entered into by DALO. However, all divisions of the Danish Ministry of Defence, including all units of the Danish Defence subject to the command of the Chief of Defence is entitled to use the Agreement.
Lot 3: RHIBS and RHIBL
Lot 3 concerns the acquisition of the two boat types, Rigid Hull Inflatable Boats Small (with outboard engine) (“RHIBS”) and Rigid Hull Inflatable Boats Large (with outboard engines) (“RHIBL”), for the Royal Danish Navy, cf.
Appendix A.1 and Appendix A.2 to the Contract for Lot 3.
The Agreement is entered into by DALO. However, all divisions of the Danish Ministry of Defence, including all units of the Danish Defence subject to the command of the Chief of Defence is entitled to use the Agreement.
Section III: Legal, economic, financial and technical information
The candidate must use the European single procurement document (electronic version, hereafter ESPD) and provide the following information in the ESPD:
— Information regarding experience with, as a minimum, 1 (one) similar delivery (reference), cf. section II.1.4) and II.2.4), in regard to the lot or lots in respect of which the tenderer has submitted an offer, carried out within the past 3 years, prior to the deadline for the submission of the offer, cf. Part IV, section C.
The tenderer may either submit an ESPD for each lot, on which the tenderer submits an offer, or the tenderer may submit one ESPD for both or all 3 lots, on which the tenderer submits an offer. If the tenderer submits one ESPD for both or all 3 lots, the list of references (stated in section IV.C of the ESPD), cf. section III.1.3) of the Contract Notice, should clearly state which lot(s) the reference in question is relevant for.
The list should preferably include a short description of each delivery, including a clear indication of which specific parts of the deliveries that are similar to the supplies as described in section II.1.4) for the lot(s) in question, in regard to the lot or lots in respect of which the tenderer has submitted an offer. Hence, it should for the individual reference/delivery clearly be stated which lot(s) the delivery is relevant for. The description should also include a description of the tenderers participation/role in the performance of the deliveries. The description should contain the date of the deliveries, the size and value of the deliveries, the recipients of the deliveries (specific names/countries are preferred, but not necessary; if no country specific information is included, the tenderer is asked to provide as much generic information as possible about the delivery). When specifying the date for the deliveries, the tenderer should state the date of commencement and completion. If this is not possible, e.g. because the delivery in question is performed on an ongoing basis according to a framework agreement, the description of the deliveries should nonetheless contain information on how the date is set.
Only the deliveries (references) performed at the time of the deadline for submission of the offer will be considered when assessing if the minimum requirement for suitability stated below is fulfilled. If the delivery in question is ongoing, it is only the part of the supplies performed and completed at the time of the deadline for the submission of the offer which will be included in the assessment of the delivery.
A tenderer may rely on the technical and professional capacity of other entities (e.g. a parent or sister company or a sub supplier), irrespective of the legal nature of the relations between the tenderer and the entity or entities on which the tenderer relies. In this case, the tenderer shall ensure that an ESPD from the entity or entities on which the tenderer relies is submitted along with the tenderers own ESPD. The entity or entities’ ESPD must equally provide the information listed above.
The tenderer will not be required to present further documentation for the technical and professional capacity (i.e. the information stated in the ESPD is considered sufficient). However, DALO reserves the right to contact the tenderer and/or the recipients of the deliveries in order to verify the information stated in Part IV, section C in the ESPD, including details on the specified dates of the performance of the deliveries.
The tenderer must demonstrate experience with as a minimum 1 (one) similar delivery within the past 3 years, prior to the deadline for the submission of the offer.
A “similar delivery” shall be understood as follows:
— Lot 1; A similar delivery (reference) is a delivery of an inflatable boat type, on which an outboard engine can not be attached, cf. section II.1.4) of the Contract Notice,
— Lot 2; A similar delivery (reference) is a delivery of an inflatable boat type, on which an outboard engine can be attached, cf. section II.1.4) of the Contract Notice,
— Lot 3; A similar delivery (reference) is a delivery of a rigid hull/hulled inflatable boat type with an outboard engine, cf. section II.1.4) of the Contract Notice.
In connection with delivery of the first batch of each boat type, the deliverables have to pass a Sea acceptance test (SAT) in accordance with Appendix G for the relevant lot, cf. clause 3.3 of the contract.
Reference is made to the tender documents regarding payment terms. Invoicing must be done in accordance with the applicable Danish legislation on public payments. At present, this is Danish consolidation act. Nº 798 of June 2007 which requires electronic invoicing. Exact terms are stated in the contract.
No particular legal form is required. If the contract is awarded to a group of suppliers (e.g. a consortium), the participants shall undertake joint and several liabilities and to appoint one supplier to represent the group.
The framework agreement must be conducted in consideration of social responsibility (CSR) and it contains a labour clause, please see Annex B for further information.
Section IV: Procedure
Section VI: Complementary information
If the same legal entity is a part of or in any other way participates in several offers, the tenderers shall ensure that the same legal entity’s participation does not provide for opportunity for mutual coordination of their offers. DALO reserves the right to request the tenderers to establish and reassure DALO that the same legal entity’s participation does not threaten the transparency and distort competition.
DALO demands that the tenderer and each of the legal entities whose capacities the tenderer relies on undertake joint and several liability for the performance of the contract.
The use of the ESPD is a precondition for participation in the procurement procedure, cf. § 148 of the Public Procurement Act. DALO shall require that the tenderer apply the ESPD as preliminary evidence that the tenderer is not subject to the grounds of exclusion stipulated in §§ 135 and 136 of the said Act, that the tenderer fulfils the minimum requirement for suitability fixed in accordance with § 140, cf. section III.1.3).
The tenderers and, if relevant, the participants in the group of entities and/or supporting entities, must use the electronic version of the ESPD.
DALO has prepared an ESPD (an XML-file) available at EU-Supply. DALO strongly encourages the tenderer to use this XML-file when completing the ESPD. For further information see clause 5.2 of the Instructions to Tenderers.
Regarding Contract Notice section II.1.6): Since the procurement is divided into lots the tenderer is asked to state in the ESPD Part II, section A which lot or lots the offer concerns. Please note, that a tenderer can only submit one offer for each lot.
As stated in section III.1.3), the tenderer may either submit an ESPD for each lot, on which the tenderer submits an offer, or the tenderer may submit one ESPD for both or all three lots.
If the tenderer submits offers on 2 or all 3 lots, it shall appear clearly which of the lots a stated reference concerns. Thus, DALO strongly encourages the tenderer to submit an ESPD for each lot.
Regarding contract notice Section IV.2.4): Please note that, even though the tender/offer must be in English, all or some of the required documentation to be supplied in connection with the delivery of each boat has to be in Danish, cf. Appendix A.1 and Appendix A.2 for each lot.
Prior to decision on award of the contract, DALO shall require that the tenderer to whom DALO intends to award the contract presents documentation for the information stated in the ESPD, cf. §§ 151-155 of the said Act. If a tenderer relies on the capacity of other entities, cf. section III.1.3), the tenderer shall upon request provide statements of support or other documentation proving that the tenderer has access to the necessary technical and professional capacity, and that the entity referred to has a legal obligation to the tenderer. If such documentation is not provided, DALO cannot consider the technical and professional capacity of the other entity or entities. DALO has prepared a template to be used to confirm the legal obligation which is available at EU-Supply. DALO strongly encourages the tenderers to use this form. However, it is emphasized that it is the sole responsibility of the tenderer that the information provided fulfils the requirements.
DALO shall exclude a tenderer from participation in the procurement procedure, if the tenderer is subject to one of the compulsory grounds for exclusion in §§ 135 and 136 of the said Act unless the tenderer has provided sufficient documentation that the tenderer is reliable in accordance to § 138 of the said Act. Please note that certain voluntary exclusion grounds in Directive 2014/24/EU on public procurement have been made compulsory in § 136 of the said Act.
DALO reserves the right — but is not obliged — to use the remedies provided for in Section 159(5) of the Public Procurement Act if applications or offers do not fulfil the formalities of the tender documents.
Nævnenes Hus, Toldboden 2
Viborg
8800
Denmark
Telephone: +45 72405600
E-mail: klfu@naevneneshus.dk
Internet address:https://erhvervsstyrelsen.dk/klagevejledning-0
Complaints regarding public procurements and decisions subject to Chapter II or III of the Public Procurement Act, which does not concern a candidate not being invited to tender, must in accordance with § 7(2) of the Act on the complaints board for public procurement be filed with the complaints board for public procurement within:
1) 45 calendar days after the Contracting Authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date).
2) 30 calendar days starting the day after the Contracting Authority has informed the tenderers in question, that the Contracting Authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision.
3) 6 months starting the day after the Contracting Authority has sent notification to the candidates/tenderers involved that the Contracting Authority has entered into the framework agreement, cf. § 2(2) or § 171(4) of the Public Procurement Act, provided that the notification included a short account of the relevant reasons for the decision.
4) 20 calendar days starting the day after the Contracting Authority has published a notice concerning his decision to uphold the contract, cf. § 185(2) of the Public Procurement Act.
The complainant must inform the Contracting Authority of the complaint in writing at the latest simultaneously with the lodge of the complaint to The Complaints Board for Public Procurement stating whether the complaint has been lodged in the stand-still period, cf. § 6(4) of the Act on The Complaints Board for Public Procurement. If the complaint has not been lodged in the stand-still period, the complainant must also state whether it is requested that the appeal is granted delaying effect, cf. § 12(1) of the said Act.
The e-mail of The Complaints Board for Public Procurement is stated in section VI.4.1.
The Complaints Board for Public Procurement’s own guidance note concerning complaints is available at the internet address stated in section VI.4.1.
Carl Jacobsens Vej 35
Valby
2500
Denmark
Telephone: +45 41715000
E-mail: kfst@kfst.dk
Internet address:http://www.kfst.dk